A Multimedia Museum of Arkansas History, People, and Culture
Old State House Museum: Home
 
Visitor Services
Collections
Exhibits
Educational Programs
Museum Store
Museum Store
 
Visitor Services

Hours & Location

History of a Landmark
Historical Overview
The Fatal Knife Fight
OSH in the Civil War
The Brooks-Baxter War
Medical School Days
Clinton Campaigns
1996-1999 Restoration
More OSH History

Events Calendar

Virtual Tour

Columns

Trapnall Hall

Press Releases

Links to Other Sites


 
Join our Mailing List

Old State House Survey
Shop Our Store















Home » General Information » History of a Landmark » Recent Renovation

Printer Friendly Printer Friendly

The Solution

The following solutions for the foundation problems were developed:

   —10' deep pits were dug under the exterior walls in six foot increments, and the existing foundation rock was removed.
   —Reinforcing steel was placed in the pit, and concrete poured to create a concrete pier.
   —Upon adequate curing, the rock foundation between each pit was removed to allow a 24" deep concrete grade beam to be poured.

Lastly, noticeable sagging of the wooden floors had occurred on the second level, which houses the legislative chambers. This is typical in older buildings; the wooden floor joists that support the flooring will slowly crush soft brick wall pockets where they rest, and create the sagging.

So that future generations will be able to enjoy the Old State House, these effects of age and use were corrected by:

  • Removal of a 3' strip of plaster ceiling along all exterior walls on the first floor, exposing the floor joists and masonry bearing pockets
  • Repair and reinforcement of damaged joist ends (with steel plates)
  • Repair of beam pockets, addition of 2' band of masonry tuck pointed all around the building where joist pockets exist, and replacement and repainting of the ceiling

The Natural and Cultural Resources Council awarded the Old State House $2 million dollars [funds from the Real Estate Transfer Tax]. In 1996, the governor's office allocated $1 million from the emergency fund and another $400,000 from the Americans with Disabilities Act (ADA) compliance funds. [During this renovation, a new ADA-compliant elevator was added, as well as accessible bathrooms.] The remaining funds were provided from other grant sources, including the Department of Arkansas Heritage.